Construction activities
An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of the total project programme.
The term ‘duration’ refers to the length of time needed to complete an activity.
The term 'path' refers to an activity or an unbroken sequence of activities in a project network. The critical path is the longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration.
‘Float’ is the time available for an activity in addition to its planned duration. For more information see: Programme float.
‘Free float’ is the amount of time that an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity.
A hanging activity is an activity not linked to any preceding or successor activities.
'Impact' is the effect a change has on an activity or the effect a change to one activity has
on another activity.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that: ‘…Each work package comprises a number of activities to be performed. Each activity can be assigned to only a single work package. Each activity is a stepping stone towards completion of its parent work package.’
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines an activity as: ‘A definable and measurable unit of work. Each activity has a start date, an end date and a duration.’
The glossary of statistical terms, published by the Organisation for Economic Co-operation and Development (OECD), states: ‘An activity is a process, i.e. the combination of actions that result in a certain set of products.’
[edit] Related articles on Designing Buildings
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.